LES TRAVAUX EN 2011

03 FEVRIER : MISE EN PLACE DE LA PASSERELLE  QUI RELIERA  LA RUE DU RUISSEAU ET LE SENTIER QUI LONGE LE NACEY EN DIRECTION DU " PATIS" .

26 AVRIL : REMPLACEMENT DES 2 POMPES DU PUIT DE CAPTAGE DES EAUX USEES AU LOTISSEMENT LE "PATIS" PAR M.G.E.

27 AVRIL : COMMENCEMENT DES CHEMINS FORESTIERS ET AGRICOLES PAR ROUX T.P.S.

10 FEVRIER : L' ENTREPRISE S.J.E. COMMENCE LES TRAVAUX DE RENATURATION DU NACEY.

26 MAI : DEMONTAGE DES TUILES DE LA GRANGE RUE DU CHATEAU.

17 JUIN : TRAVAUX DES CHEMINS.

05 AVRIL : S.J.E. EST EN TRAIN DE CREUSER LE LIT MINEUR DU NACEY.

19 JUILLET : DEMONTAGE DU MONUMENT AUX MORTS .

01 AOUT : DESTRUCTION DE LA GRANGE PAR MR BELLENEY.


24 AOUT : FAUCHAGE DU NACEY PAR MR MARTIN.


31 AOUT : SUITE A UN ORAGE , MR MILLERET DE CHARCENNE REMPLACE  2

LAMPADAIRES RUE DU CHATEAU.

05 SEPTEMBRE : RETOUR DE ROUX T.P.S. POUR LA FIN DES TRAVAUX.

RENATURATION DU NACEY (SUITE) .


26 SEPTEMBRE : REMPLACEMENT DE CANIVEAUX DEVANT LE 17 DE LA RUE

PRINCIPALE PAR LES EMPLOYES COMMUNAUX.


27 SEPTEMBRE :  VIDANGE DE LA GRANDE FONTAINE POUR NETTOYAGE ET

RECHERCHE DE LA FUITE AU NIVEAU DU " CHATEAU D ' EAU "  PAR LES EMPLOYES COMMUNAUX .

29 SEPTEMBRE : MISE EN PEINTURE DES LETTRES GRAVEES SUR LE MONUMENT

AUX MORTS PAR PASCAL ET OLIVIER.

29 SEPTEMBRE: DECAISSEMENT DE L'EMPLACEMENT DES FONDATIONS DU

MONUMENT AUX MORTS PAR MR VUILLEQUEZ.

04 OCTOBRE:COULAGE DES FONDATIONS DU MONUMENT PAR MR VUILLEQUEZ A

L'AIDE D'UNE TOUPIE DE DIJON BETON.

06 OCTOBRE:FIN DE LA MISE EN PEINTURE DES LETTRES DU MONUMENT PAR

PASCAL OLIVIER ET NOEL.

12 OCTOBRE: COULAGE DE LA DALLE DU MONUMENT AUX MORTS ,SUR LAQUELLE

LES PREMIERES PIERRES SERONT POSEES.

20 OCTOBRE:TRANSFERT DES PIERRES DU MONUMENT VERS SON NOUVEL EMPLACEMENT  PAR PIERRE ,OLIVIER, NOEL ET GILLES.

22 OCTOBRE:MISE EN PLACE DES 4 PIERRES DE L'EMBASE DU MONUMENT.

26 OCTOBRE:COFFRAGE DE LA REHAUSSE DU PUITS DE CAPTAGE DES EAUX USEES

DE LA RUE PRINCIPALE PAR LES EMPLOYES COMMUNAUX.

26 OCTOBRE:INSTALLATION DU MONUMENT AUX MORTS PRES DE LA MAIRIE PAR

PIERRE,CHRISTIAN,NOEL,OLIVIER ET GILLES.

27 OCTOBRE:COULAGE DE LA REHAUSSE DU PUITS PAR JEAN LUC,PIERRE,NOEL ET GILLES.

28 OCTOBRE:JOINTOIEMENT DES PIERRES DU MONUMENT PAR JEAN LUC.

10 NOVEMBRE:POSE DU MAT AUX COULEURS PRES DU MONUMENT.

17 NOVEMBRE:ENTRETIEN DE LA MACHINERIE DU CLOCHER PAR ENTREPRISE

BODET.

28 NOVEMBRE:REHAUSSE D'UN REGARD A PROXIMITE DU PUITS DE CAPTAGE DES EAUX PAR LES EMPLOYES COMMUNAUX.

29 NOVEMBRE: REALISATION D'UN BI-COUCHE DANS LE LOTISSEMENT DE LA

TUILERIE.

02 DECEMBRE: POUR LE PASSAGE DES GAINES D'EAU POTABLE ET D'ELECTRICITE ,

STEPHANE DUREY A EFFECTUE DE NOMBREUSES TRANCHEES A COTE DU PUITS .

DONT UNE , POUR EVACUER L'EAU PROVENANT D'UNE SOURCE.